Nangal flyover construction work has resumed

[ad_1]

Harjot Singh Bains: Due to the efforts of Punjab Cabinet Minister Harjot Singh Bains, the work of placing steel guard on the railway line between Nangal Flyover has started. Giving information in this regard, Cabinet Minister Harjot Singh Bains said that this part was the biggest reason for the delay in the construction of Nangal Flyover.

He said that 15 steel girders are to be placed on one side of the railway line, out of which a total of 5 have been placed earlier and out of the 5 main girders to be placed on the main railway line after the approval of the Railway Department, 3 steel girders have been placed today. And the work of placing the remaining 2 steel girders will also be completed by 4th July 2023.

Harjot Singh Bains said that the efforts to start a side avajai with the help of the steel guard placed today will be completed very soon. He said that a side bridge will be prepared and opened for public very soon.

Bains expressed regret and said that the work of this flyover, which started on January 6, 2018, was supposed to be completed in 2020, but if those who represented the constituency in the previous government and held positions in the government had made some effort, the people of Nangal would not have faced any problems. would have faced and neither would the economy of this city have been hurt.

It is worth mentioning here that the shifting work of Kusht Ashram is also going on very fast and full cooperation is being given by all the residents of Kusht Ashram due to which the road connecting with the flyover will also be ready soon.

note: You can download our app to read breaking news in Punjabi. You can also follow Pro Punjab TV on social media platforms Facebook, Twitter and Instagram.

TV, FACEBOOK, YOUTUBE from First every the news to read for Download do PRO PUNJAB TV APP

APP Download to do for Link ‘on Click do:

Android: https://bit.ly/3VMis0h

iOS: https://apple.co/3F63oER

[ad_2]

Source link